RECENT PROJECTS

Project

Raozan 25 MW Dual Fuel Power Plant Project

Contract Signed on 23-03-2011 Expected Date of Commissioning June 2012. Construction Work...

Project

150 MW POWER PLANT PROJECT OF BPDP-RPCL POWERGEN LTD. AT KADDA, GAZIPUR

TENDER RECEIVED ON 03-05-2011

Project

52 MW DUAL FUEL RPCL-GAZIPUR POWER PLANT PROJECT.

Contract Signed on 24-08-2010 Expected Date of Commissioning November 2011....

Project

Mymensingh Power Station (MPS)

Mymensingh Power Station (MPS) Capacity: 210 MW: (4X35MW Open Cycle GT &...

PreviousStopNext

NEWS

Dec-20, 2011 12:00 AM

16th Annual General Meeting

AGM Date & Time: 26th December,2011 at 7:00 pm

read more
Dec-08, 2011 12:00 AM

Best Employee Award-2011

Best employees of RPCL have been awarded in the National Electricity Week-2011

read more
Dec-08, 2010 12:00 AM

RPCL rewarded for Mymensingh Power Station...

RPCL rewarded for Mymensingh Power Station as the best Power Plant in National Electricty Week,2010.

read more
Show All

Related Links

project image

PROJECT DETAIL - Mymensingh Power Station (MPS)

PreviousStopNext

Mymensingh Power Station (MPS)

Capacity: 210 MW:

(4X35MW Open Cycle GT & 1X70 MW Steam Turbine)

  1. Phase - I   : 2X35 MW Gas turbine (Commissioned in November 1999)
  2. Phase –II : 2X35 MW Gas turbine(Commissioned in December 2000)
  3. Phase –III: 1X70 MW Steam Turbine (Commissioned in July 2007)
  4. Project Cost
    of
    Mymensingh Power Station (MPS)

Total Project Cost for 3 Phases: BDT 15,078,738,882.00

  1. Phase-I: BDT 2,359,150,203
  2. Phase-II:BDT 1,673,588,679
  3. Phase-III:BDT 11,046,000,000

b)  Financing:
i) Equity: BDT 667,939,035
Equity raised from REB and Five PBSs
ii) Debt: BDT 1,691,211,168
Debt raised from ADB long term loan of $36.386 million.

Phase-II :

a)Total Project Cost : BDT 1,673,588,679
b) Financing :


i) Equity: BDT 840,708,965
Equity raised from Eight PBSs

ii) Debt: BDT 520,000,000
Debt raised from REB
iii)  RPCL own source: BDT 312,879,714 

Phase-III :

a) Total Project Cost       : BDT 11,046,000,000
b) Cost incurred so far   : BDT 9,197,523,020 
c) Financing:
i)  Equity               : BDT 909,465,000
Equity raised from 9 PBSs
ii) Debt :               BDT 3,840,000,000 
Debt raised from REB &11 PBSs
iii) RPCL own fund            : BDT 6,296,535,000

 

Major Plant Machinery
(MPS Phase I & II)

 

Features of Plant Machinery:

  1. Gas Turbines                                      : Type PG6551B & PG6561B (GE, France)
  2. Generators                                         : Type T600C(ALSTOM, France).
  3. Unit Step-Up Transformers         : 35/50MVA (Hyundai, Korea).
  4. Substation & Switchgear               : ABB, Sweden.

Special Features:

  1. Modern & Environment Friendly Technology.
  2. Enclosed by Acoustic Walls to reduce noise.
  3. Dry Low NOx (DLN) Combustion System to reduce Nox (Nox below 15 ppm).
  4. Mark-V & Distributed Control System (DCS).
  5. Plant design includes multiple layers of backup control levels to ensure high availability.
  6. Plant Control is state of the art with computerized generation control and a complete monitoring system of  all significant data.

Major Plant Machinery
(Phase-III)

Features of Plant Machinery:

  1. Steam Turbine                                  : Model: NK 90/3.2 (Siemens, Germany).
  2. Generator                                           : Model: TLRI 100/36 (Siemens, Germany)

                                                                                  Capacity: 77.3 MW

  1. Unit Step-Up Transformer                           : 70/100 MVA (Siemens, Germany).
  2. Substation & Switchgear                               : Siemens, Germany.
  3. Boiler (HRSG)                                                     : Standard Fasel, Netherland.
  4. Air Cooled Condenser (ACC)                       : Air flow Capacity – 82.5 Kg/s,                                                                                                                                      Balcke Dour GmbH, Germany.
  5. Water Treatment Unit (WTU)                     : Capacity – 11.5 m3/hr Chirst, Netherland

Special Features:

  1.  
    • Modern & Environment Friendly Technology
    • Continuous Exhaust Monitoring System (CEMS)
    • PCS-7 Control System
    • Additional feature of Station Control & Maintenance
    • MIS Server (Maintenance Information System)
    • CMMS (Computerised Maintenance Management System)
    • THOMS ( Thomassen Online Monitoring System) remote monitoring
  2.